Duffield Hall Lab 313 Nitride MOCVD
Project Description
1. Demolish existing laboratory space to enable existing lab hood to be relocated on the other side of the lab.
2. Modify existing facility services, and install new services, to support new laboratory equipment,
3. Install owner provided laboratory equipment, connect equipment to facility services, and support equipment commissioning.
Estimated Construction Budget
$435,000-$445,000
Pre-Bid Meeting
133 Humphreys Service Building
Deadline for RFI
Bid Opening
eBuilder Bidding Module
Project Schedule
Start: Within five (5) days of written authorization to proceed
Completion: February 16, 2025
Architect/Engineer
Hallam ICS
Invited Bidders
Name | Phone | Fax |
---|---|---|
Edger Enterprises of Elmira, Inc. | 607-733-9664 | 607-733-3951 |
LeChase Construction Services, LLC | 315-423-0015 | 315-423-0054 |
Murnane Building Contractors, Inc. | 315-432-0490 | 315-432-0655 |
Purcell Construction Corporation | 315-782-1050 | 315-782-5820 |
Streeter Associates, Inc. | 607-734-4151 | 607-732-2952 |
The Pike Company, Inc. | 585-271-5256 | 585-271-3101 |
W. L. Kline, Inc. | 607-724-6637 | 607-724-6650 |
Welliver McGuire, Inc. | 607-535-5400 | 607-535-9254 |
Project Documents
To obtain documents, visit the Planroom.