Project Description

1.    Removal of aging thermal camera installations and associated equipment
2.    Installation of updated surveillance cameras and associated mounting hardware and equipment
3.    Updated installation of network infrastructure

Estimated Construction Budget

$240,000-$245,000

Pre-Bid Meeting

102C Humphreys Service Building/Zoom

Deadline for RFI

Bid Opening

eBuilder Bidding Module

Project Schedule

Start: Within Ten (10) of written authorization to proceed
Completion: August 1, 2025

Architect/Engineer

Cornell Facilities Engineering 

Invited Bidders

Name Phone Fax
John Mills Electric, Inc. 607-734-4111 607-734-4150
Matco Electric Corporation 607-729-4921 607-729-0932
Schuler-Haas Electric Corp 585-325-1060 585-325-2364