Ensure Compliance with the current Building Codes of New York State for all SUNY- and Contract College-owned buildings.

    • Plan review during Schematic Design, Design Development, and Construction Documents.
    • Walk the site during construction with Project Manager and Contractor weekly.
    • Witness system tests scheduled by Project Manager or Contractor
    • Final walk through before Certificates are issued with Project Manager and Contractor.
  •  

  • Issue Permits

    Construction Building Permits
    • Asbestos Abatement Permits – Blanket Permits
    • Demolition Permits
    • Systems Modification Permits – Fire Protection Systems
    • Hot Works Permit
    • Temporary Heat Permit (During Construction)
    • Tent Permits

  • Issue Certificates

    • Temporary Certificate of Occupancy
    • Permanent Certificate of Occupancy