Guide to Obtaining Contract Colleges Facilities Project Permits and Certificates
Obtaining Contract Colleges Facilities SUNY Project Permits
Only the SUNY Code Enforcement Official /Authority Having Jurisdiction for Contract Colleges Facilities at Cornell University shall issue Permits for all work within or on statutory facilities, properties or holdings within the Cornell University Contract Colleges system. Only the Contract Colleges Facilities SUNY CEO/AHJ (Jim Yarbrough 607-254-6371) shall make the determination of a permit’s status, requirements and its remaining in effect. The Codes of New York State prohibit the Owner and the A&E from making codes compliance administrations. Only the authority having jurisdiction (AHJ) has permitting or final codes determination capacity.
A-Permits issued through CCF – CEO / AHJ are:- Asbestos Abatement Permit
- Demolition Permit
- Construction Permit
- Building Permits
- System(s) Modifications Permit
- Hot Work Permits
- Temporary Certificate of Occupancy
- Permanent Certificate of Occupancy
- Certificate of Completion
- One set of stamped and signed Construction / Bid documents – drawings and specifications – includingBuilding Code Summary- for review and permit records (The earlier documents are reviewed the sooner apermit can be readied.).
- Letter from the A&E of record stating that project complies with all current applicable codes and is readyfor permitting.
- Name of General Contractor for the project
- Project’s construction value
- Contractors' Site Specific Safety Plan that is specific to the project for which a permit is being requested.
- Electric certifications for all rough-ins and final inspection: Certified Independent Electrical InspectionAgency, as accepted by the SUNY CEO / AHJ.
- Certification of Fire Detection and Suppression systems – Installer’s NFPA Certification
- Certification of plumbing testing witnessed by SUNY CEO /AHJ.
- HVAC & Hydronic systems balancing reports – Mechanical Engineer of Record accepted.
- Special inspections reports reviewed and accepted by A&E of record
- Letter from A&E stating that project has been constructed to the design documents, including any approvedchanges, and the project is ready for Beneficial Occupancy.
- Completed SUNY Pre-occupancy checklist signed by the A&E and Project Manager.
- EH&S Fire Safety must confirm to me that the fire detection and suppression systems are properly installedand fully operational (EH&S Contact: Dan Phillips 607- 255- 8200).
- CU Pipe Shop must dye test all storm and sanitary sewer connections or internal piping modifications andconfirm to the CEO/AHJ that there are no cross-connections (CU Pipe Shop Contact: 607-255-4754).
- EH&S must confirm to the CEO/AHJ that all eyewashes and fume hoods are EH&S tested and ready foruse by building occupants. (EH&S Contact Ellen Sweet 315-730-8896). Note: The designing A&E must accept the system(s) and certify to the CEO/AHJ that the systems are installed incompliance with the A&E’s stamped design, including any A&E approved design changes, and all applicable codes. EH&S confir mations to the CEO/AHJ that EH&S has witnessed specific test or system(s) operations and find themready for acceptance and University operation upon turnover, no occupancy or completion permit will be issued.