Utility Shutdown Request 30865
Request Status
Request Number
30865
Emergency Request
No
Requestor's Name
Chas Porter
Requestor's Email
cbp22@cornell.edu
Requestor's Phone
16072278775
Department/Company
Pipe Shop
Request Start Date/Time
Request End Date/Time
Systems Affected
HX2 preheat
Areas Affected
HX2 preheat
Comments
Building HX2 has a backup HX, can isolate only HX2 and should not affect building
EHS Request
No
EHS Reason for Shutdown
replace leaking gaskets
Work Order Numbers
13129423
Assignment History
<ul><li>Requested by Chas Porter - 04-01-2021 08:47AM</li><li>Submitted by Chas B. Porter, IV - 04-01-2021 08:47AM</li><li>Email notification is sent by Chas B. Porter, IV - 04-01-2021 8:47AM to: fcscrequest@cornell.edu,cbp22@cornell.edu</li><li>Status changed to Canceled by Emily Ann Sickmon - 04-01-2021 10:59AM</li><li>Email notification is sent by Emily Ann Sickmon - 04-01-2021 10:59AM to: fcscrequest@cornell.edu,cbp22@cornell.edu,ls249@cornell.edu,jrs579@cornell.edu,kmn64@cornell.edu,eas454@cornell.edu</li></ul>
Terms & Conditions
Yes
Affected Facility
EHS City Tie
On
EHS Horns
On
EHS Zones
On
EHS Devices
On
EHS SRB
On
EHS Relays
On
EHS Spare
On
EHS PIVA
On
EHS Ground Values
On
EHS Drains Open
On
EHS Air Control
On
EHS Jockey Pump
On
EHS Fire Pump
On
EHS Control Values
On
EHS Other
On
EHS Loops
On