Meinig Fieldhouse

Overview

The Meinig Fieldhouse will offer 91,150 gsf of new indoor practice, competition and recreation space. It will accommodate full-sized men’s lacrosse, women’s lacrosse, and football fields, and provide an excellent indoor soccer training surface. Additionally, thousands of students who participate in club and intramural sports each year will enhance their physical and mental health year-round with access to this facility.

The new 107,520 gsf exterior multi-purpose field will provide additional access for varsity athletics, campus recreation, and club and intramural sports. This centrally located field is a fundamental piece of Cornell's commitment to being a health-promoting campus by offering spaces that inspire meaningful connections among all Cornellians.

Read more here

Project team

  • Nicki Moore – Director of Athletics
  • James Kazukietas – Assistant Director SCL Facilities
  • Paul Stemkoski – FCS Director, Project Management
  • Dustin Sutherland – FCS Project Manager
  • Jake Duell – FCS Construction Manager
  • Robert Titus – Designer, Sasaki
  • Robert Lee – Designer, Sasaki
  • John Fritz – Project Executive, Welliver
  • Eddie Eddington – APM, Welliver
  • Doug Sheerer – Superintendent, Welliver

Project schedule

  • Design Approval: May 2024

  • Authorize Construction: Oct 2024

  • Est. Completion: May 2026

Project statistics

  • Project Size: 358,000 GSF Total
  • Bldg. Size: 94,000 GSF w/ mezzanine
  • Ext. Field Turf Size: 92,000 GSF
  • Field Hockey at GFR Size includes field, parking, and road: 172,000 GSF
  • Construction Cost/GSF: $192
  • Total Project Budget: $68.7M (includes Field Hockey Field)