Utility Shutdown Request 34261
Request Status
              
          Request Number
              34261
          Emergency Request
              No
          Requestor's Name
              Michael F. Dempsey
          Requestor's Email
              mfd26@cornell.edu
          Requestor's Phone
              6073271820
          Department/Company
              CZ Control
          Request Start Date/Time
              Request End Date/Time
              Request Shop Assistance
          
      Systems Affected
              Preheat, Reheat, Radiation
          Areas Affected
              Entire Building Heat Will Be At Reduced 25% Capacity
          Comments
              VHX-2 will need to be shut down to replace it's F&T steam trap, VHX-1 is designed to carry 75% of demand load to supplied buildings.  The scheduled day will be close to 40 degrees outside air temperature.
          EHS Request
              No
          EHS Reason for Shutdown
              To replace F&T steam trap on VHX-2
          Work Order Numbers
          15037787
              Notification Comments
              Eric.N Approves shut down 1/31/23
Joy.J Approved shut down 1/31/23
Pat.G Approved shut down 2/1/23
David.P approved shut down 2/1/23
Todd.S Approved shut down 2/1/23
          Joy.J Approved shut down 1/31/23
Pat.G Approved shut down 2/1/23
David.P approved shut down 2/1/23
Todd.S Approved shut down 2/1/23
Assignment History
              <ul><li>Requested by Michael F. Dempsey  -  01-31-2023 01:02PM</li><li>Submitted by Michael F. Dempsey  -  01-31-2023 01:02PM</li><li>Email notification is sent by Michael F. Dempsey  -  01-31-2023  1:02PM to: fcscrequest@cornell.edu,mfd26@cornell.edu</li><li>Assigned to Emily Ann Sickmon by Emily Ann Sickmon -  01-31-2023  1:17PM</li><li>Status changed to Assigned by Emily Ann Sickmon  -  01-31-2023  1:17PM</li><li>Email notification is sent by Emily Ann Sickmon  -  01-31-2023  1:17PM to: eas454@cornell.edu</li><li>Record updated by Emily Ann Sickmon  -  01-31-2023  3:17PM</li><li>Status changed to Pending Approval by Emily Ann Sickmon  -  02-01-2023  11:28AM</li><li>Email notification is sent by Emily Ann Sickmon  -  02-01-2023  11:28AM to: fcscrequest@cornell.edu,ls249@cornell.edu,jrs579@cornell.edu,kmn64@cornell.edu,eas454@cornell.edu</li><li>Approved by Kara M Nash  -  02-01-2023  11:31AM</li><li>Status changed to Scheduled by Kara M Nash  -  02-01-2023  11:31AM</li><li>Email notification is sent by Kara M Nash  -  02-01-2023  11:31AM to: fcscrequest@cornell.edu,fcs-shutdown-l@cornell.edu,mfd26@cornell.edu,wpe2@cornell.edu,peg4@cornell.edu,en285@cornell.edu,jaj5@cornell.edu,dlp96@cornell.edu,tjs358@cornell.edu</li></ul>
          Terms & Conditions
              Yes
          Affected Facility
          
      Notify People
          fac-1024: William Esty; wpe2@cornell.edu; +1 (607) 254-8045; level-1
          fac-1024: Patrick Graham; peg4@cornell.edu; +1 (607) 2276502; level-1
          fac-2032: Eric Nichols; en285@cornell.edu; 607-255-2200; level-1
          fac-2081: Joy Jones; jaj5@cornell.edu; +1 (607) 255-9743; level-1
          fac-2084: David Pawelczyk; dlp96@cornell.edu; +1 (607) 255-2338; level-1
          Todd Searles; tjs358@cornell.edu; 607-280-9902
              Assignee
              eas454
          Approver
              kmn64
          EHS City Tie
              On
          EHS Horns
              On
          EHS Zones
              On
          EHS Devices
              On
          EHS SRB
              On
          EHS Relays
              On
          EHS Spare
              On
          EHS PIVA
              On
          EHS Ground Values
              On
          EHS Drains Open
              On
          EHS Air Control
              On
          EHS Jockey Pump
              On
          EHS Fire Pump
              On
          EHS Control Values
              On
          EHS Other
              On
          EHS Loops
              On