Skip to main content

Cornell University

Utility Shutdown Request 34144

Submitted by jpc349 on
Request Status
Request Number
34144
Emergency Request
No
Requestor's Name
Jason Cragle
Requestor's Email
jpc349@cornell.edu
Requestor's Phone
6072262825
Department/Company
FCS E&PM
Request Start Date/Time
Request End Date/Time
Systems Affected
AHU-4
Areas Affected
Lab 281
Comments
Existing AHU-4 demolition and new AHU-4 installation for the Stocking Hall East Food Processing Lab HVAC construction project on the 2nd floor. Project Manager Jason Cragle can be contacted to discuss details jpc349@cornell.edu or (607) 226-2825. Ben Ribstein with Kimble is the site supervisor, cell phone is (315) 576-1015.
EHS Request
No
EHS Reason for Shutdown
Construction
Notification Comments
John.J Approved shut down 1/12/2023
Assignment History
<ul><li>Requested by Jason Cragle - 01-11-2023 04:51PM</li><li>Submitted by Jason Paul Cragle - 01-11-2023 04:51PM</li><li>Email notification is sent by Jason Paul Cragle - 01-11-2023 4:51PM to: fcscrequest@cornell.edu,jpc349@cornell.edu</li><li>Assigned to Emily Ann Sickmon by Emily Ann Sickmon - 01-12-2023 8:22AM</li><li>Status changed to Assigned by Emily Ann Sickmon - 01-12-2023 8:22AM</li><li>Email notification is sent by Emily Ann Sickmon - 01-12-2023 8:22AM to: eas454@cornell.edu</li><li>Status changed to Pending Approval by Emily Ann Sickmon - 01-12-2023 9:34AM</li><li>Email notification is sent by Emily Ann Sickmon - 01-12-2023 9:34AM to: fcscrequest@cornell.edu,ls249@cornell.edu,jrs579@cornell.edu,kmn64@cornell.edu,eas454@cornell.edu</li><li>Approved by Kara M Nash - 01-12-2023 12:05PM</li><li>Status changed to Scheduled by Kara M Nash - 01-12-2023 12:05PM</li><li>Email notification is sent by Kara M Nash - 01-12-2023 12:05PM to: fcscrequest@cornell.edu,fcs-shutdown-l@cornell.edu,jpc349@cornell.edu,jpj4@cornell.edu</li></ul>
Terms & Conditions
Yes
Affected Facility
Notify People
fac-1063: John Jantz; jpj4@cornell.edu; +1 (607) 7936992; level-1
Assignee
Approver
EHS City Tie
On
EHS Horns
On
EHS Zones
On
EHS Devices
On
EHS SRB
On
EHS Relays
On
EHS Spare
On
EHS PIVA
On
EHS Ground Values
On
EHS Drains Open
On
EHS Air Control
On
EHS Jockey Pump
On
EHS Fire Pump
On
EHS Control Values
On
EHS Other
On
EHS Loops
On