Replace Emergency Generator – Poultry Farm SUCF# 161102
Project Description
Provide a 300-kW diesel yard generator and emergency power to various buildings at the Poultry Farm Complex. Scope of work also includes a roof replacement and new siding at the existing generator shed.
Estimated Construction Budget
$1.0 Million - $1.1 Million
Pre-Bid Meeting
133 Humphreys Service Building/Zoom
Deadline for RFI
RFIs to: facilitiescontracts@cornell.edu
Bid Opening
133 Humphreys Service Building and via Zoom
Project Schedule
Completion: Within 365 Calendar Days of written authorization to proceed
Architect/Engineer
Facilities Engineering, Cornell University
Invited Bidders
Cost Per Set
Hard Copy: $49.00
Electronic Copy: $49.00
Project Documents
To obtain documents, visit the Planroom.