Carl A. Kroch Library Storm Drain Repair
Project Description
1. Replace storm drain system piping at Carl A. Kroch Library.
2. Provide sprinkler, electrical, ceiling, and soffit modifications to accommodate the storm drain system piping work.
3. Extend leak detection to new storm drain piping.
Estimated Construction Budget
$575,000-$600,000
Pre-Bid Meeting
101 Humphreys Service Building/Zoom
Deadline for RFI
Bid Opening
Trimble Bidding Module
Project Schedule
Start: Within seven (7) days of written authorization to proceed.
Completion: July 16, 2027
Architect/Engineer
LaBella Associates, D.P.C.
Invited Bidders
| Name | Phone | Fax |
|---|---|---|
| J&K Plumbing and Heating Company Inc | 607-772-1666 | 607-724-4048 |
| Frey & Campbell, Inc. | 607-569-2297 | 607-569-3668 |
| John W. Danforth Company | 716-832-1940 | 716-832-2388 |
| Kimble, Inc | 607-734-4123 | 607-734-4199 |
| Postler & Jaeckle Corp. | 585-423-6255 | 585-546-4316 |
| Upstate Piping and Construction Services | 607-425-4691 | 607-767-6342 |
Project Documents
To obtain documents, visit the Planroom.