Ward Center Renovation New York Consortium for Space Technology (NYCST)
Project Description
Project to include demo and abatement, steel framing, concrete sidewalks, fire protection, carpentry, masonry, and MEP work.
Estimated Construction Budget
$950,000-$1,000,000
Pre-Bid Meeting
133 Humphreys Service Building/Zoom
Deadline for RFI
Bid Opening
eBuilder Bidding Module
Project Schedule
Start: Within fourteen (14) days of written authorization to proceed.
Completion: August 31, 2026
Architect/Engineer
Richard McElhiney Architects LLC
Invited Bidders
| Name | Phone | Fax |
|---|---|---|
| Edger Enterprises of Elmira, Inc. | 607-733-9664 | 607-733-3951 |
| LeChase Construction Services, LLC | 315-423-0015 | 315-423-0054 |
| Streeter Associates, Inc. | 607-734-4151 | 607-732-2952 |
| W. L. Kline, Inc. | 607-724-6637 | 607-724-6650 |
| Welliver McGuire, Inc. | 607-535-5400 | 607-535-9254 |
Project Documents
To obtain documents, visit the Planroom.