Exterior Path of Travel Signage
Project Description
Installation of exterior signage showing the accessible routes and entrances around Cornell’s main campus.
Estimated Construction Budget
$250,000-$255,000
Pre-Bid Meeting
101 Humphreys Service Building
Deadline for RFI
Bid Opening
eBuilder Bidding Module
Project Schedule
Start: Within five (5) days of written authorization to proceed
Completion: November 7, 2025
Architect/Engineer
Cornell Facilities Engineering
Invited Bidders
| Name | Phone | Fax |
|---|---|---|
| Andrew R. Mancini Associates, Inc | 607-754-7070 | 607-786-0410 |
| F. E. Jones Construction, Inc. | 607-348-0045 | 607-348-0050 |
| LeChase Construction Services, LLC | 315-423-0015 | 315-423-0054 |
| Streeter Associates, Inc. | 607-734-4151 | 607-732-2952 |
| W. L. Kline, Inc. | 607-724-6637 | 607-724-6650 |
| Welliver McGuire, Inc. | 607-535-5400 | 607-535-9254 |
Project Documents
To obtain documents, visit the Planroom.