Roof Replacement - Hedrick Hall SUCF #341023

Project Description

1.    Remove existing roof membrane system down to wood plank decking and install new asphalt and modified bitumen roofing system.
2.    Remove existing dormer and install new framing and decking where dormer is removed.
3.    Relocate existing attic ductwork where dormer is removed and replace dormer window exhaust and intake louvers with rooftop mounted insulated curb units.

Estimated Construction Budget

$870,000-$880,000

Pre-Bid Meeting

Geneva Jordan Hall Classroom 210, 630 North Street, Geneva, New York

Deadline for RFI

RFIs to: facilitiescontracts@cornell.edu

Bid Opening

102C Humphreys Service Building and via Zoom

Project Schedule

Completion: 120 Calendar Days

Architect/Engineer

Cornell University Facilities Engineering 

Invited Bidders

Bidding open to all contractors

Cost Per Set

Hard Copy: $49.00
Electronic Copy: $49.00

Project Documents

To obtain documents, visit the Planroom.