Skip to main content

Cornell University

Utility Shutdown Request 39658

Submitted by crd42 on
Request Status
Request Number
39658
Emergency Request
No
Requestor's Name
Christopher Dinse
Requestor's Email
crd42@cornell.edu
Requestor's Phone
607-342-4877
Department/Company
Projects
Request Start Date/Time
Request End Date/Time
Systems Affected
panel LP-2 (120/208 power)
Areas Affected
Basement cordoor lights, general receptacles in a few room, a couple samll AC units.
Comments
please refer to panel directory to see what will be shut off.
EHS Request
No
EHS Reason for Shutdown
Tie in new sub panel
Work Order Numbers
16842081
Notification Comments
Lillian Henry confirmed shutdown 4/11/25
Assignment History
<ul><li>Requested by Christopher Dinse - 04-09-2025 08:14AM</li><li>Submitted by crd42 - 04-09-2025 08:14AM</li><li>Email notification is sent by crd42 - 04-09-2025 8:14AM to: fcscrequest@cornell.edu,crd42@cornell.edu</li><li>Assigned to dnm64 by dnm64 - 04-09-2025 1:31PM</li><li>Status changed to Assigned by dnm64 - 04-09-2025 1:31PM</li><li>Email notification is sent by dnm64 - 04-09-2025 1:31PM to: dnm64@cornell.edu</li><li>Assigned to kmn64 by kmn64 - 04-11-2025 1:12PM</li><li>Status changed to Pending Approval by kmn64 - 04-11-2025 1:12PM</li><li>Email notification is sent by kmn64 - 04-11-2025 1:12PM to: fcscrequest@cornell.edu,ls249@cornell.edu,jrs579@cornell.edu,kmn64@cornell.edu,jo422@cornell.edu,eas454@cornell.edu,dnm64@cornell.edu,rg833@cornell.edu</li><li>Approved by kmn64 - 04-14-2025 8:34AM</li><li>Status changed to Scheduled by kmn64 - 04-14-2025 8:34AM</li><li>Email notification is sent by kmn64 - 04-14-2025 8:34AM to: fcscrequest@cornell.edu,fcs-shutdown-l@cornell.edu,crd42@cornell.edu,leh12@cornell.edu,wld2@cornell.edu,pjv4@cornell.edu</li></ul>
Terms & Conditions
Yes
Affected Facility
Notify People
fac-1062: Lillian Henry; leh12@cornell.edu; +1 (607) 9729166; level-1
fac-1062: Bill Dowdall; wld2@cornell.edu; +1 (607) 592-7421; level-2
fac-1062: Paul Viscuso; pjv4@cornell.edu; +1 (607) 254-8780; level-3-CIT Equipment (Elec/HVAC)
Assignee
Approver
EHS City Tie
On
EHS Horns
On
EHS Zones
On
EHS Devices
On
EHS SRB
On
EHS Relays
On
EHS Spare
On
EHS PIVA
On
EHS Ground Values
On
EHS Drains Open
On
EHS Air Control
On
EHS Jockey Pump
On
EHS Fire Pump
On
EHS Control Values
On
EHS Other
On
EHS Loops
On