Duffield Hall 213 and 324 Laboratory Renovations Bid Preparation
Project Description
Provide select renovations of Room 213 to create a temporary Characterization Lab, provide a complete renovation of Room 324 for a new permanent Characterization Lab, and provide a complete renovation of Room 213 following these renovations for a new TLE Lab.
Estimated Construction Budget
$1,225,000 - $1,275,000
Pre-Bid Meeting
133 Humphreys Service Building
Deadline for RFI
Bid Opening
eBuilder Bidding Module
Project Schedule
Start: Within seven (7) days of written authorizatin to proceed
Completion: December 13, 2024
Architect/Engineer
Ashley McGraw Architects D.P.C.
Invited Bidders
Name | Phone | Fax |
---|---|---|
Edger Enterprises of Elmira, Inc. | 607-733-9664 | 607-733-3951 |
LeChase Construction Services, LLC | 315-423-0015 | 315-423-0054 |
Murnane Building Contractors, Inc. | 315-432-0490 | 315-432-0655 |
Streeter Associates, Inc. | 607-734-4151 | 607-732-2952 |
The Pike Company, Inc. | 585-271-5256 | 585-271-3101 |
W. L. Kline, Inc. | 607-724-6637 | 607-724-6650 |
Welliver McGuire, Inc. | 607-535-5400 | 607-535-9254 |
Project Documents
To obtain documents, visit the Planroom.