Replace Water Filtration System - Kenneth Post Lab SUCF #161067

Project Description

Replace the existing reverse osmosis (“RO”) equipment and modify distribution piping and controls to improve water quality and system monitoring at the Kenneth Post Lab.

Estimated Construction Budget

$280,000-$300,000

Pre-Bid Meeting

102C Humphreys Service Building/Zoom

Deadline for RFI

RFIs to: facilitiescontracts@cornell.edu

Bid Opening

133 Humphreys Service Building and via Zoom

Project Schedule

Completion: 180 Calendar Days

Architect/Engineer

LaBella Associates, D.P.C.

Invited Bidders

Bidding open to all contractors

Cost Per Set

Hard Copy: $49.00
Electronic Copy: $49.00

Project Documents

To obtain documents, visit the Planroom.