Project Description
The work includes demolition and construction to the lighting electrical system as required for replacement of the light fixtures in seventeen (17) of the twenty (20) Greenhouses at Boyce Thompson Institute (BTI). The replacement lighting fixtures aim to match the fixtures at the remaining three (3) Greenhouses. The existing installations in three (3) Greenhouses will have the panel enclosures updated to the proper rating.
Estimated Construction Budget
$300,000-$320,000
Pre-Bid Meeting
101 Humphreys Service Building/Zoom
Deadline for RFI
RFIs to: facilitiescontracts@cornell.edu
Bid Opening
133 Humphreys Service Building and via Zoom
Project Schedule
Completion: 460 Calendar Days
Architect/Engineer
Cornell University Facilities Engineering
Invited Bidders
Cost Per Set
Hard Copy: $49.00
Electronic Copy: $49.00
Project Documents