Skip to main content

Raw Products Building Chiller Replacement SUCF #341027

Project Description

Contractor to remove the existing air-cooled process chiller in the Geneva Raw Products Building and replace it with a new air-cooled process chiller. The electrical service supplying the existing chiller shall remain, however the disconnect will be replaced with new.

Estimated Construction Budget

$425,000-$450,000

Pre-Bid Meeting

Geneva Barton Laboratory A134 Conference Room/Zoom

Deadline for RFI

RFIs to: facilitiescontracts@cornell.edu

Bid Opening

133 Humphreys Service Building and via Zoom

Project Schedule

Completion: 120 Calendar Days

Architect/Engineer

Cornell University Facilities Engineering

Invited Bidders

Bidding open to all contractors

Cost Per Set

Hard Copy: $49.00
Electronic Copy: $49.00

Project Documents

To obtain documents, visit the Planroom.