Raw Products Building Chiller Replacement SUCF #341027
Project Description
Contractor to remove the existing air-cooled process chiller in the Geneva Raw Products Building and replace it with a new air-cooled process chiller. The electrical service supplying the existing chiller shall remain, however the disconnect will be replaced with new.
Estimated Construction Budget
$425,000-$450,000
Pre-Bid Meeting
Geneva Barton Laboratory A134 Conference Room/Zoom
Deadline for RFI
RFIs to: facilitiescontracts@cornell.edu
Bid Opening
133 Humphreys Service Building and via Zoom
Project Schedule
Completion: 120 Calendar Days
Architect/Engineer
Cornell University Facilities Engineering
Invited Bidders
Cost Per Set
Hard Copy: $49.00
Electronic Copy: $49.00
Project Documents
To obtain documents, visit the Planroom.