Maple Ave 120 Studio Fitout
Project Description
1. Complete interior renovation of an existing 1,850 sf. open office space into a new broadcast studio suite for Cornell’s University Relations group.
2. Code required ADA improvements to the accessible path of travel to the new broadcast studio suite.
Estimated Construction Budget
$600,000-$625,000
Pre-Bid Meeting
133 Humphreys Service Building/Zoom
Deadline for RFI
Bid Opening
Project Schedule
Start: Within fourteen (14) days of written authorization to proceed.
Completion: January 2, 2025
Architect/Engineer
Chiang O'Brien Architects, DPC
Facilitiescontracts@cornell.edu
Invited Bidders
Name | Phone | Fax |
---|---|---|
Andrew R. Mancini Associates, Inc | 607-754-7070 | 607-786-0410 |
F.E. Jones Construction of NY, LLC | (607) 348-0045 | (607) 348-0050 |
LeChase Construction Services, LLC | 315-423-0015 | 315-423-0054 |
Murnane Building Contractors, Inc. | 315-432-0490 | 315-432-0655 |
Purcell Construction Corporation | 315-782-1050 | 315-782-5820 |
Streeter Associates, Inc. | 607-734-4151 | 607-732-2952 |
W. L. Kline, Inc. | 607-724-6637 | 607-724-6650 |
Welliver McGuire, Inc. | 607-535-5400 | 607-535-9254 |
Project Documents
To obtain documents, visit the Planroom.