Garden Ave. Water Distribution Improvements
Project Description
Contractor to provide all labor, materials, and equipment necessary to complete the Garden Avenue Water Distribution Improvements at Cornell University, including installation of 560 LF of new water main piping along Garden Avenue and adjacent building connections; connections to existing water mains and installation of two (2) new hydrants, nine (9) valves, and associated appurtenances; and provide all required excavation, trenching, and coordination with existing utilities.
Estimated Construction Budget
$320,000-$330,000
Pre-Bid Meeting
133 Humphreys Service Building/Zoom
Deadline for RFI
Bid Opening
Trimble Bidding Module
Project Schedule
Start: Within 7 days of written authorization to proceed.
Completion: August 6, 2026
Architect/Engineer
T. G. Miller, P. C.
Invited Bidders
| Name | Phone | Fax |
|---|---|---|
| Buono Construction | 607-231-7339 | NA |
| Economy Paving Co., Inc. | 607-756-2819 | 607-756-4742 |
| Laubacker Enterprises, Inc. | 716-534-4870 | NA |
| Merlo Inc. | 814-322-1545 | NA |
| Smith Site Development, LLC | 607-692-4204 | 607-692-2705 |
| Wenzel Landscaping, LLC | 607-732-7781 | NA |
Project Documents
To obtain documents, visit the Planroom.