Faculty Startup Renovations at Corson Mudd and Lab of Ornithology
Project Description
1. Provide renovations in two (2) buildings – Corson Mudd and the Lab of Ornithology. Renovations will create new laboratory, office and storage space for new faculty.
2. Work includes mechanical, electrical, plumbing (MEP), fire protection modifications, finishes, lighting, flooring, ceilings, furnishings, and fume hood installation.
Estimated Construction Budget
$975,000-$1,000,000
Pre-Bid Meeting
133 Humphreys Service Building/Zoom
Deadline for RFI
Bid Opening
eBuilder Bidding Module
Project Schedule
Start: Within thirty (30) days of written authorization to proceed.
Completion: August 15, 2025
Architect/Engineer
SWBR Architecture, Engineering & Landscape Architecture, DPC
Facilitiescontracts@cornell.edu
Invited Bidders
Name | Phone | Fax |
---|---|---|
Andrew R. Mancini Associates, Inc | 607-754-7070 | 607-786-0410 |
F.E. Jones Construction of NY, LLC | (607) 348-0045 | (607) 348-0050 |
LeChase Construction Services, LLC | 315-423-0015 | 315-423-0054 |
Murnane Building Contractors, Inc. | 315-432-0490 | 315-432-0655 |
PAC & Associates of Oswego Inc. | 315-343-7937 | 315-343-9554 |
Purcell Construction Corporation | 315-782-1050 | 315-782-5820 |
Streeter Associates, Inc. | 607-734-4151 | 607-732-2952 |
W. L. Kline, Inc. | 607-724-6637 | 607-724-6650 |
Welliver McGuire, Inc. | 607-535-5400 | 607-535-9254 |
Project Documents
To obtain documents, visit the Planroom.