Corson Mudd Hall Vivarium Renovation
Project Description
1. Renovation of approximately 536 square feet of existing office space into a wet laboratory on the first floor of Corson Hall. The scope of work is to include construction of a vivarium space that will house fish. Demolition includes the removal of flooring, partitions, ceilings, lighting, and MEP systems; including removal of asbestos materials as hazardous materials.
2. Rooms E148 and E150 will be substantially gutted and reconstructed with finishes, ceilings, MEPFP systems and laboratory casework. Additionally, room E150A will house chilled water equipment.
Estimated Construction Budget
$450,000-$465,000
Pre-Bid Meeting
102C Humphreys Service Building
Deadline for RFI
Bid Opening
eB Bidding Module
Project Schedule
Start: Within seven (7) days of written authorization to proceed
Completion: August 15, 2025
Architect/Engineer
SWBR Architecture, Engineering & Landscape Architecture, DPC
facilitiescontracts@cornell.edu
Invited Bidders
Name | Phone | Fax |
---|---|---|
Anthony J Giammarino Associates LLC | 607-203-1387 | 607-203-1390 |
F.E. Jones Construction of NY, LLC | (607) 348-0045 | (607) 348-0050 |
Andrew R. Mancini Associates, Inc | 607-754-7070 | 607-786-0410 |
Edger Enterprises of Elmira, Inc. | 607-733-9664 | 607-733-3951 |
LeChase Construction Services, LLC | 315-423-0015 | 315-423-0054 |
Murnane Building Contractors, Inc. | 315-432-0490 | 315-432-0655 |
Purcell Construction Corporation | 315-782-1050 | 315-782-5820 |
Streeter Associates, Inc. | 607-734-4151 | 607-732-2952 |
W. L. Kline, Inc. | 607-724-6637 | 607-724-6650 |
Welliver McGuire, Inc. | 607-535-5400 | 607-535-9254 |
Project Documents
To obtain documents, visit the Planroom.