Skip to main content

Comstock Hall 5th Floor Lab and Support Space Renovations

Project Description

1.    Renovate approximately 3,900 SQFT in Rooms 5119, 5121A, 5121, 5123, 5123A, 5123B, and 5132 on the 5th floor of Comstock Hall.  Work includes renovation of existing lab space that will be occupied by a new faculty member.  
2.    Demolition includes removal of existing casework, most ceilings, lighting, a controlled environmental room, and removal of asbestos containing materials as hazardous material.  These spaces will be reconstructed with new ceiling, partition wall, lighting, finishes, MEP systems, fume hood, and laboratory casework.  

Estimated Construction Budget

$900,000-$1,000,000

Pre-Bid Meeting

102C Humphreys Service Building/Zoom

Deadline for RFI

Bid Opening

eBuilder Bidding Module

Project Schedule

Start: Within ten (10) days of written authorization to proceed.
Completion: January 29, 2027

Architect/Engineer

SWBR Architecture, Engineering & Landscape Architecture, DPC

Invited Bidders

Name Phone Fax
Andrew R. Mancini Associates, Inc 607-754-7070 607-786-0410
Dan Brown Construction 607-205-1001 NA
Fahs Construction Group 607-724-1835 607-724-2361
LeChase Construction Services, LLC 315-423-0015 315-423-0054
Robertson Development & Construction, LLC 607-257-5050 607-257-9981
Streeter Associates, Inc. 607-734-4151 607-732-2952
W. L. Kline, Inc. 607-724-6637 607-724-6650
Welliver McGuire, Inc. 607-535-5400 607-535-9254

Project Documents

To obtain documents, visit the Planroom.