Project Description
Phase 1 work addressed site drainage and grading around the Clara Dickson Hall building. Roof repair work during Phases 2, 3 and 4 will occur during the summers of 2026, 2027 and 2028, and include the following:
1. Remove, Salvage, and Reinstall existing slate roofing
2. Install new slate roofing
3. Provide Ice Protection
4. New Flashing Systems
5. Wood Deck Replacement
6. Dormer Wood Siding Repairs
7. Isolated Repairs to Wood Cornice
8. Rebuilding of Masonry Chimneys
9. Masonry Repairs at fire separation walls and vicinity of cornice
Estimated Construction Budget
$7,250,000-$7,500,000
Pre-Bid Meeting
102C Humphreys Service Building
Deadline for RFI
Bid Opening
eB Bidding Module
Project Schedule
Start: Within fourteen (14) days of written authorization to proceed
Completion: August 1, 2028
Invited Bidders
| Name | Phone | Fax |
|---|---|---|
| F.E. Jones Construction of NY, LLC | (607) 348-0045 | (607) 348-0050 |
| Andrew R. Mancini Associates, Inc | 607-754-7070 | 607-786-0410 |
| LeChase Construction Services, LLC | 315-423-0015 | 315-423-0054 |
| Murnane Building Contractors, Inc. | 315-432-0490 | 315-432-0655 |
| Northland Associates, Inc. | 315-451-3722 | 315-451-3655 |
| Purcell Construction Corporation | 315-782-1050 | 315-782-5820 |
| Streeter Associates, Inc. | 607-734-4151 | 607-732-2952 |
| Welliver McGuire, Inc. | 607-535-5400 | 607-535-9254 |
Project Documents
To obtain documents, visit the Planroom.