Beebe Hall CU Maker HUB Renovations
Project Description
1. New entry addition, exterior porch, and elevator.
2. New flooring, ceilings, painting, casework, and doors.
3. New HVAC, plumbing, electrical, fire suppression, fire alarm, security and access control, communications, and exterior site improvements.
4. Project to receive LEED Silver accreditation.
Estimated Construction Budget
$9.0M-9.2M
Pre-Bid Meeting
133 Humphreys Service Building/Zoom
Deadline for RFI
Bid Opening
Trimble Bidding Module
Project Schedule
Start: Within seven (7) days of written authorization to proceed.
Completion: December 31, 2027
Architect/Engineer
Ashley McGraw Architects D.P.C.
Invited Bidders
| Name | Phone | Fax |
|---|---|---|
| Andrew R. Mancini Associates, Inc | 607-754-7070 | 607-786-0410 |
| Edger Enterprises of Elmira, Inc. | 607-733-9664 | 607-733-3951 |
| F.E. Jones Construction of NY, LLC | (607) 348-0045 | (607) 348-0050 |
| Robertson Development & Construction, LLC | 607-257-5050 | 607-257-9981 |
| LeChase Construction Services, LLC | 315-423-0015 | 315-423-0054 |
| Streeter Associates, Inc. | 607-734-4151 | 607-732-2952 |
| The Pike Company, Inc. | 585-271-5256 | 585-271-3101 |
| W. L. Kline, Inc. | 607-724-6637 | 607-724-6650 |
| Welliver McGuire, Inc. | 607-535-5400 | 607-535-9254 |
Project Documents
To obtain documents, visit the Planroom.